Development application OZS-2023-0025, SPA-2023-0071
20 Lynch St
20 Lynch St is the site of 4 applications on the City of Brampton's record (zoning by-law amendment, site plan, pre-application consultation) in Ward 3. It has been approved.
- Approved
- Closed Approved; Site Plan Approved; Closed
- 20 Lynch St
- 3
- OZS-2023-0025, SPA-2023-0071, SPA-2026-0078, PRE-2022-0189
- December 23, 2022
Proposed, in the record's words: “Zoning By-law Amendment to permit a maximum building Height of 13 Storeys, and Site Specific Yard Setbacks. For Peel Memorial Hospital Phase 2”. Latest dated step on the record: application received, June 10, 2026. Files OZS-2023-0025, SPA-2023-0071.
- Approved
- Closed Approved; Site Plan Approved; Closed
- 20 Lynch St
- 3
- OZS-2023-0025, SPA-2023-0071, SPA-2026-0078, PRE-2022-0189
- December 23, 2022
What is proposed
Zoning By-law Amendment to permit a maximum building Height of 13 Storeys, and Site Specific Yard Setbacks. For Peel Memorial Hospital Phase 2.
Site Plan Application for Peel Memorial Hospital Expansion
While final details of the PMP2 project are finalized, the team is eager to maintain the project’s schedule and expedite construction activity on the site to the greatest extent possible. There are a range of known early works construction activities that are required to be undertaken on the site in any scenario, which Osler and DevCo would like to enable via this limited SPA application. Proposed early works include: • Installation of a Concrete Pressure Pipe (CPP) valve chamber on John Street • Relocation of a light pole on Centre Street to accommodate future construction access • Installation of hoarding, silt fences, gates, turnstiles, and related sidewalk overhead protection surrounding the PMP2 construction site • Grading and stone prep work for a temporary construction office complex and parking area on the northeast portion of the site, related adjustments to catch basins, and establishing temporary power fed from the PMP1 building • Relocation and/or removal of park furniture and landscape improvements within hoarding areas to prepare the site for future development (such as hardscape areas, trees, and plantings) • Closing a portion of Lynch Street and opening a temporary site access road; related adjustments to fire routes • Rerouting existing fire service and domestic water for the PMP1 building (shifting southeast to avoid PMP2 construction area), and installing check valves • Adjustments to existing signage and wayfinding impacted by hoarding along John Street and Centre Street, including relocation and replacement as required to maintain safe and clear access Please see the cover letter for further information.
Hospital Expansion
What has happened
Every date in the municipality’s record for this project’s applications, in order. Nothing is inferred between them.
Application received · Pre-application consultation PRE-2022-0189
Application received · Site plan SPA-2023-0071
Application received · Zoning by-law amendment OZS-2023-0025
Application received · Site plan SPA-2026-0078
The record shows nothing dated after June 10, 2026; the next recorded step appears here when the municipality enters it.
The 4 applications
The source links these records to one another (the same planning file or the same site), so they are shown as one project. Each is listed as the municipality records it.
Zoning by-law amendment
Site plan
Site plan
Pre-application consultation
Sources
- Planning applications (Brampton GeoHub layers) — checked November 27, 2026