Major road projects in Brampton

The big road jobs in Brampton now and in the next few years: the City's widenings of Goreway Drive, Countryside Drive and Heritage Road, Peel Region's widenings of Steeles Avenue, Mayfield Road and Dixie Road, the downtown streetscape and the LRT.

Summary

The City of Brampton is widening Goreway Drive and Countryside Drive to four lanes now, with Heritage Road expected to follow in 2028. Peel Region plans to widen Steeles Avenue west of Chinguacousy Road to six lanes from 2027 to 2030 and is widening sections of Mayfield Road and Dixie Road through 2031. Downtown, the streetscape project on Main and Queen streets runs to December 2027.

Last verified

Administered by The City of Brampton builds City roads; Peel Region builds Regional roads such as Steeles, Mayfield and Dixie; Metrolinx builds the LRT. Every answer below was checked against its source on November 27, 2026; the source is linked under each one.


City of Brampton roads

When will the Goreway Drive widening be finished?

The City is widening Goreway Drive to four lanes between Cottrelle Boulevard and Countryside Drive, with intersection improvements, some multi-use paths, streetscaping and landscaping. The section from Jacksonville Drive to Tortoise Court is complete and open, and work has moved to the final section between Tortoise Court and Countryside Drive, with one lane open each way and local access kept.

The City's update does not give a completion date.

Source: City of Brampton, Capital Construction Project Updates

What other road widenings is the City of Brampton planning?

The City lists Countryside Drive, being widened to four lanes with multi-use paths from west of the future Arterial A2 to Regional Road 50 (construction under way); Heritage Road, Steeles Avenue to north of Financial Drive, to four lanes (design 60 per cent done, construction expected in 2028); the Clark Boulevard extension and Eastern Avenue widening between Rutherford Road and Kennedy Road (design 30 per cent, construction expected from 2029); McVean Drive phase 2, Countryside Drive to Mayfield Road (design done, construction beyond 2030); and Cadetta Road, led by Peel Region (construction expected from spring 2027).

City of Brampton capital road projects

City of Brampton capital road projects
ProjectLimitsStageConstruction
Countryside Drive wideningWest of future Arterial A2 to Regional Road 50Under constructionOngoing
Goreway Drive wideningCottrelle Boulevard to Countryside DriveFinal section under wayOngoing
Heritage Road wideningSteeles Avenue to north of Financial DriveDesign 60% completeExpected 2028
Clark Boulevard extension and Eastern AvenueRutherford Road to Kennedy RoadDesign 30% in progressExpected from 2029
McVean Drive phase 2Countryside Drive to Mayfield RoadDesign completeBeyond 2030
Cadetta Road improvements (Peel Region lead)Regional Road 50 to endDesign 95% completeExpected from spring 2027

Table source: City of Brampton, Capital Construction Project Updates

Source: City of Brampton, Capital Construction Project Updates

When will the downtown Brampton construction end?

The City's Downtown Brampton Streetscape Project, on Main Street between Nelson Street and Wellington Street and Queen Street between Mill Street and Chapel Street, started in September 2024 and is scheduled to end in December 2027. It replaces sidewalks with granite pavers and curbs and installs new infrastructure, in phases that close one side of the street at a time.

Source: City of Brampton, Downtown Brampton Streetscape Project


Peel Region roads

Is Steeles Avenue being widened in Brampton?

Yes, west of Chinguacousy Road. Peel Region's timeline widens Steeles Avenue from two to six lanes between Chinguacousy Road and Mississauga Road, with utility relocation from early 2026 to early 2027 and construction from early 2027 to mid 2029, and from four to six lanes between Mississauga Road and Winston Churchill Boulevard, with construction from early 2028 to the end of 2030.

Source: Peel Region, Working with You to deliver Steeles Avenue: construction timeline (2026-2030)

What is happening on Mayfield Road?

Peel Region is widening Mayfield Road, which it lists as a Brampton and Caledon project, in sections. Hurontario Street to Chinguacousy Road (two to six lanes) is scheduled for construction from early 2026 to the end of 2026; Dixie Road to Bramalea Road (five to six lanes) runs to the end of 2028; Chinguacousy Road to Mississauga Road and Airport Road to The Gore Road are set for construction from mid 2027 to 2029; and Heart Lake Road to Hurontario Street is planned for mid 2029 to the end of 2031.

Peel Region Mayfield Road widening sections

Peel Region Mayfield Road widening sections
SectionWideningConstruction
Hurontario Street to Chinguacousy Road2 to 6 lanesEarly 2026 to end of 2026
Dixie Road to Bramalea Road5 to 6 lanesEarly 2026 to end of 2028
Chinguacousy Road to Mississauga Road2 to 5 lanesMid 2027 to mid 2029
Mississauga Road to Winston Churchill BoulevardOn hold due to Highway 413On hold
Airport Road to The Gore Road2 to 5 lanesMid 2027 to end of 2029
Coleraine Drive to Highway 502 to 4 lanesMid 2027 to mid 2030
The Gore Road to Coleraine Drive2 to 5 lanesLate 2028 to end of 2030
Heart Lake Road to Hurontario Street4 to 6 lanesMid 2029 to end of 2031

Table source: Peel Region, Working with You to deliver Mayfield: Road construction timeline (2026-2031)

The Region lists the section from Mississauga Road to Winston Churchill Boulevard as on hold because of Highway 413.

Source: Peel Region, Working with You to deliver Mayfield: Road construction timeline (2026-2031)

What is happening on Dixie Road?

Peel Region's Dixie Road timeline shows noise walls on the west side between Queen Street and Bovaird Drive completed; widening from two to four lanes between Countryside Drive and 2 km north of Mayfield Road scheduled from early 2026 to the end of 2028; widening from four to six lanes between Bovaird Drive and Countryside Drive from mid 2027 to the end of 2028; and widening from four to six lanes between Queen Street and Bovaird Drive from early 2029 to late 2031. Noise walls between Springtown Trail and Countryside Drive are scheduled for late 2026 to mid 2027.

Source: Peel Region, Working with You to deliver Dixie: Road construction timeline (2026-2031)

Where can I see all Peel Region construction in Brampton?

On Peel Region's interactive construction map, which shows watermain, sanitary sewer and Regional road projects. The Region's current projects page also links timelines for Steeles Avenue, Mayfield Road, Dixie Road, Mississauga Road, Winston Churchill Boulevard and northeast Brampton, and lets you sign up for email notices. For City of Brampton projects, use the City's BramptonWorks map.

Source: Peel Region, Current construction projects


Transit construction

How is LRT construction affecting Hurontario Street in Brampton?

Metrolinx is building the Hazel McCallion Line along Hurontario Street to the Brampton Gateway Terminal at Steeles Avenue. Its February 12, 2026 update said track work was complete at most intersections and along the guideway, with stops taking shape. Metrolinx says Hurontario will go from three lanes each way to two once the guideway is built, and it has not announced an opening date.

Source: Metrolinx, CPG (Rapid Transit) State of the Network

Sources

Every factual claim above traces to one of these documents.

  1. City of Brampton

    Capital Construction Project Updates

    Retrieved November 27, 2026

  2. City of Brampton

    Downtown Brampton Streetscape Project

    Retrieved November 27, 2026

  3. Peel Region

    Current construction projects

    Retrieved November 27, 2026

  4. Metrolinx

    CPG (Rapid Transit) State of the Network

    Published February 12, 2026 · Retrieved November 27, 2026