Status: On hold. The municipality lists the application as on hold, for example while it waits for more material.

Development application T01E12.002

7324 Kennedy Road

7324 Kennedy Road is a zoning by-law amendment on the City of Brampton's record in Ward 3. It is listed as on hold.

Last checked November 27, 2026City of BramptonHow we know
Publisher
City of Brampton
Source dataset
Planning applications (Brampton GeoHub layers)
Retrieved
November 27, 2026
Licence
Creative Commons Attribution 4.0 International (CC BY 4.0) Terms
From the source
the project and application names · file numbers · status · dates where recorded · the description of the proposal
Derived by BramptonIQ
the stage label · grouping of linked applications into one project · area and ward by the site's location · what is nearby
BramptonIQ’s words
the summary sentence
Kept current
Rebuilt from the municipality's source by the data pipeline; each run is dated, and changes between runs are listed on the changes page.

Proposed, in the record's words: “The Hurontario Light Rapid Transit (HuLRT) Project involves 2 of the 15 traction power substations (TPSSs) to be installed along the LRT alignment in Brampton, a Gateway Transit Station on the south side of Steeles…”. Latest dated step on the record: application received, June 11, 2018. File T01E12.002.

As of November 27, 2026 · City of Brampton

Data currency. Read from the City of Brampton source on November 27, 2026. The source was last edited November 27, 2026. Only 7,923 of 9,373 records carry a date; the newest is November 16, 2026. Planning applications (Brampton GeoHub layers)

At a glance
Stage
On hold
Status on the record
Inactive
Address
7324 Kennedy Road
Ward
3
File number
T01E12.002
First application received
June 11, 2018
Aerial view of 7324 Kennedy Road, Brampton
Imagery: Esri, Maxar, Earthstar Geographics

What is proposed

The Hurontario Light Rapid Transit (HuLRT) Project involves 2 of the 15 traction power substations (TPSSs) to be installed along the LRT alignment in Brampton, a Gateway Transit Station on the south side of Steeles Avenue, and an operation, maintenance and storage facility (OMSF) at the S/W corner of Kennedy Road and Highway 407. This application is for the OMSF component of the HuLRT Project where the LRV's will be maintained, repaired, cleaned and parked overnight. COB APPLICATION - FEES WAIVED, PLANNER TO PROVIDE DOCUMENTATION TO SUPPORT THIS Uncertainty as to whether this application should be closed and whether Province wants to reactivate application.

The City of Brampton’s description of the application, as published.


What has happened

Every date in the municipality’s record for this project’s applications, in order. Nothing is inferred between them.

  1. June 11, 2018

    Application received · Zoning by-law amendment T01E12.002


The application

As the municipality records it.

  1. Zoning by-law amendmentT01E12.002

    Type
    Zoning by-law amendment (Application to Amend the Zoning By-Law)
    Status on the record
    Inactive
    Received
    June 11, 2018

Sources

Contains information licensed under CC BY 4.0 from the City of Brampton Creative Commons Attribution 4.0 International (CC BY 4.0). Figures are the municipality’s records at the date checked; a later submission can change them.